Question 196:
Which project management document describes how project deliverables will be formally accepted and validated?
A) Project charter
B) Acceptance management plan
C) Quality management plan
D) Scope statement
Correct Answer: B
Explanation:
The acceptance management plan, which is often integrated within the scope management plan or maintained as a standalone document, describes the formal processes and procedures that will be used to validate and accept project deliverables. This document establishes clear criteria and systematic approaches for determining when deliverables meet requirements and are ready for stakeholder acceptance. Understanding acceptance management is crucial for project managers because formal acceptance represents the point at which the project team’s responsibility for deliverables transfers to the customer or operational teams.
The acceptance management plan addresses multiple critical components that guide the validation and acceptance process throughout the project lifecycle. It defines specific acceptance criteria for each major deliverable or deliverable category, establishing measurable conditions that must be satisfied before acceptance can be granted. These criteria might include functional requirements that the deliverable must fulfill, performance standards that must be met, quality specifications that must be achieved, completeness requirements ensuring all components are included, and documentation requirements specifying what supporting materials must be provided.
The plan establishes the validation process that will be used to verify deliverables meet acceptance criteria. This process typically involves inspection where deliverables are examined to verify they match specifications, testing where functionality or performance is validated against requirements, demonstration where deliverables are shown operating correctly in realistic conditions, and review where documentation and supporting materials are evaluated for completeness and accuracy. The plan specifies who will conduct validation activities, what methods will be used, and what evidence must be produced to demonstrate compliance with criteria.
Question 197:
What is the primary purpose of a project team charter in establishing team norms?
A) To formally authorize the project
B) To establish team values, agreements, and working guidelines
C) To define project scope and deliverables
D) To assign budget authority to the project manager
Correct Answer: B
Explanation:
A project team charter, which is distinct from the project charter, is a document created by and for the project team that establishes shared values, agreements, and working guidelines to govern how team members will work together. This team-level document focuses on building a cohesive team culture and clarifying behavioral expectations that support effective collaboration and high performance. Understanding team charters is relevant for project managers because effective team development and clear working agreements are essential for project success, particularly when team members come from diverse backgrounds or have not worked together previously.
The project team charter typically addresses several key elements that create shared understanding about how the team will function. Team values and principles guide behavior and decision-making, establishing fundamental beliefs such as respect for all team members, transparency in communication, commitment to quality, or collaboration over competition. These values provide the cultural foundation for team interactions and help resolve questions about appropriate behavior when specific situations arise. Communication guidelines specify how team members will interact including meeting protocols, response time expectations for emails or messages, how information will be shared, and channels that will be used for different types of communication.
Decision-making processes clarify how decisions will be made and who has authority for various types of decisions. This might include consensus-based decisions for major team choices, delegated authority for technical decisions within domains of expertise, or escalation processes for decisions requiring input beyond the team. Conflict resolution approaches describe how disagreements will be addressed constructively, emphasizing direct communication, focus on issues rather than personalities, and escalation paths when conflicts cannot be resolved within the team.
Question 198:
Which risk response strategy involves monitoring the risk without taking proactive action?
A) Risk mitigation
B) Risk transfer
C) Risk avoidance
D) Risk acceptance
Correct Answer: D
Explanation:
Risk acceptance is a risk response strategy where the project team acknowledges the risk and makes a conscious decision not to take proactive action to change its probability or impact. This strategy essentially means the team is willing to accept the consequences if the risk occurs. Understanding risk acceptance is important for project managers because not all risks warrant active response, and resources should be focused on risks that justify management investment while accepting those that fall within tolerance or have low priority.
Risk acceptance can take two forms that differ in their level of preparation. Passive acceptance involves simply acknowledging the risk and taking no action unless and until the risk occurs, at which point the team will deal with consequences reactively. This approach is appropriate for low-priority risks where the cost of proactive response would exceed the expected impact if the risk materializes. Active acceptance involves developing contingency plans or allocating contingency reserves that can be used if the risk occurs, even though no action is taken to prevent it. This approach prepares for potential risk realization without investing in prevention.
The acceptance strategy is most appropriate in several situations that make proactive response unnecessary or inefficient. When the risk has very low probability or impact such that its expected value is minimal and does not justify response investment. When no cost-effective response exists that would significantly reduce the risk, making acceptance more economical than attempting mitigation that provides little benefit. When the risk falls within stakeholder risk tolerance, meaning stakeholders are comfortable with the level of exposure and do not require active management.
Risk acceptance differs from other risk response strategies in its passive approach. Unlike mitigation which actively reduces probability or impact through specific actions, acceptance takes no preventive steps. Unlike transfer which shifts risk to third parties through insurance or contracts, acceptance keeps the risk with the project.
Question 199:
What is the primary purpose of a project cost baseline in performance measurement?
A) To identify project stakeholders
B) To serve as a reference for measuring cost performance
C) To assign resources to activities
D) To track team attendance
Correct Answer: B
Explanation:
The project cost baseline is the approved time-phased budget that serves as a reference point for measuring, monitoring, and controlling overall cost performance on the project. This baseline represents the aggregated cost of all approved work packages, control accounts, and any allocated contingency reserves, distributed over time according to when costs are expected to be incurred. Understanding the cost baseline is essential for project managers because it provides the standard against which actual costs are compared to determine whether the project is within budget or experiencing cost variances that require corrective action.
The cost baseline is typically displayed as an S-curve because project spending usually starts slowly during initiation and planning when few resources are engaged, accelerates during execution when most work occurs and resources are fully deployed, and decreases during closure as work winds down and resources are released. This time-phased budget shows not just total project cost but when money will be spent throughout the project lifecycle. The baseline includes all authorized budgets for project work but typically excludes management reserves, which are held separately for unforeseen work within project scope and require management approval to access.
The cost baseline serves multiple critical purposes in project cost management and control. It provides the authorized budget for the project, establishing spending limits and enabling financial control by defining how much can be spent and when. The baseline supports earned value analysis by providing the planned value component, which represents the authorized budget for scheduled work at any point in time. It enables variance analysis by providing the standard against which actual costs are compared to calculate cost variance, which shows whether the project is under budget or over budget.
The baseline facilitates performance measurement through the cost performance index, which compares the value of work performed to actual costs incurred, indicating cost efficiency.
Question 200:
Which project management process group involves establishing the total scope and defining course of action?
A) Initiating
B) Planning
C) Executing
D) Closing
Correct Answer: B
Explanation:
The planning process group consists of processes performed to establish the total scope of the effort, define and refine objectives, and develop the course of action required to attain those objectives. This process group is where the project management plan and all subsidiary plans are developed, providing comprehensive documentation that guides project execution and control. Understanding the planning process group is essential for project managers because thorough planning establishes the foundation for project success by creating realistic, achievable plans that guide the project team.
The planning process group encompasses extensive activities that transform the high-level authorization from the project charter into detailed plans for executing and controlling the project. Scope planning involves collecting requirements from stakeholders, defining detailed project scope, and creating the work breakdown structure that decomposes deliverables into manageable components. Schedule planning develops the activity list, sequences activities based on dependencies, estimates activity durations and resources, and creates the schedule baseline showing when work will occur. Cost planning estimates costs for activities and resources, determines the budget, and establishes the cost baseline showing when money will be spent.
Quality planning identifies relevant quality requirements and standards and documents how the project will demonstrate compliance. Resource planning identifies what human and physical resources are needed, estimates quantities, and develops approaches for acquiring and managing resources. Communication planning determines stakeholder information needs and develops strategies for meeting those needs through appropriate communication methods and frequencies. Risk planning identifies risks, analyzes their probability and impact, develops response strategies, and establishes contingency reserves. Procurement planning determines what will be acquired externally and develops procurement strategies and documents. Stakeholder planning develops strategies for effectively engaging stakeholders throughout the project.
The planning process group produces the project management plan, which integrates all subsidiary plans and baselines into a comprehensive document that guides execution and control. Planning is iterative, with progressive elaboration adding detail as more information becomes available throughout the project.
Question 201:
What is the primary purpose of a project sprint backlog in agile methodologies?
A) To list all product features
B) To identify work selected for a specific iteration
C) To track project costs
D) To document lessons learned
Correct Answer: B
Explanation:
The sprint backlog is a list of work items, tasks, and deliverables that the development team commits to completing during a specific sprint or iteration. This subset of the product backlog represents the team’s plan for the upcoming iteration and includes both the selected product backlog items and the detailed tasks needed to deliver them. Understanding the sprint backlog is essential for project managers working in agile environments because it represents the team’s commitment for the iteration and guides daily work throughout the sprint.
The sprint backlog is created during sprint planning when the development team selects items from the prioritized product backlog to work on during the upcoming sprint. The team considers their capacity based on historical velocity and upcoming availability, examines the highest-priority items in the product backlog, discusses each item with the product owner to understand requirements and acceptance criteria, and negotiates which items can realistically be completed within the sprint timebox. Once items are selected, the team decomposes them into detailed tasks that represent the actual work needed to deliver the functionality. This task breakdown ensures everyone understands what needs to be done and provides granularity for tracking progress.
The sprint backlog serves multiple important purposes throughout the sprint. It provides transparency about what the team is working on during the iteration, enabling stakeholders to understand current focus without interrupting team members. The backlog guides daily work by showing what tasks need attention and who is working on what. It enables progress tracking as the team updates task status and remaining effort throughout the sprint, often visualized through burndown charts that show work remaining versus time. The backlog supports daily standup meetings where team members discuss progress, plans, and impediments while referencing current work items.
Unlike the product backlog which is owned by the product owner, the sprint backlog is owned by the development team. Team members update the sprint backlog throughout the iteration as they work on tasks, complete items, discover new work, or adjust estimates.
Question 202:
Which project document identifies both internal and external factors affecting the project?
A) Risk register
B) Environmental factors analysis
C) Assumption log
D) SWOT analysis
Correct Answer: D
Explanation:
A SWOT analysis is a strategic planning tool that identifies strengths, weaknesses, opportunities, and threats affecting the project. This technique systematically examines both internal factors such as strengths and weaknesses that are within organizational control, and external factors such as opportunities and threats that arise from the environment outside organizational control. Understanding SWOT analysis is valuable for project managers because it provides comprehensive assessment of factors that could influence project success and helps identify strategies that leverage strengths, address weaknesses, exploit opportunities, and mitigate threats.
SWOT analysis examines four distinct categories of factors that together provide holistic view of the project situation. Strengths are internal positive factors that give the project or organization advantages, such as experienced team members with relevant expertise, proven methodologies or processes that increase success probability, strong stakeholder support and organizational commitment, advanced technology or tools that enable superior solutions, or established vendor relationships that facilitate procurement. Identifying strengths helps the project team understand what capabilities and advantages they can leverage to increase success probability.
Weaknesses are internal negative factors that place the project or organization at disadvantage, such as skill gaps in critical areas requiring training or external expertise, immature or ineffective processes that reduce efficiency, limited resources or budget constraints, weak stakeholder relationships or insufficient support, or outdated technology requiring workarounds. Recognizing weaknesses enables the project team to develop strategies to address or compensate for limitations before they become critical problems.
Opportunities are external positive factors that the project could exploit for benefit, such as favorable market conditions that increase demand for project outcomes, emerging technologies that could enhance solutions, regulatory changes that create new possibilities, potential partnerships that could provide capabilities or resources, or competitor weaknesses that create competitive advantage. Identifying opportunities helps the team proactively pursue beneficial circumstances rather than discovering them too late or missing them entirely.
Question 203:
What is the primary purpose of a project performance review in monitoring and controlling?
A) To develop the project charter
B) To assess project performance against baselines and identify variances
C) To assign initial resources
D) To validate deliverables
Correct Answer: B
Explanation:
A project performance review is a systematic assessment of project performance conducted to compare actual progress and results against planned baselines and performance measurement criteria. This review identifies variances between planned and actual performance across multiple project dimensions including scope, schedule, cost, quality, and risk. Understanding performance reviews is essential for project managers because they provide the analytical foundation for determining whether corrective actions are needed to bring the project back on track or whether baselines need adjustment to reflect new realities.
Project performance reviews examine multiple performance dimensions to provide comprehensive assessment of project health. Schedule performance is evaluated by comparing actual completion dates for activities and milestones against the schedule baseline, calculating schedule variance to show whether work is ahead or behind plan, and determining schedule performance index to measure schedule efficiency. Cost performance is assessed by comparing actual expenditures against the cost baseline, calculating cost variance to show budget over or under runs, and determining cost performance index to measure cost efficiency. These earned value metrics provide integrated assessment of both schedule and cost performance.
Scope performance is evaluated by assessing whether deliverables are being completed according to specifications and whether scope changes are being properly controlled through change management processes. Quality performance is reviewed by examining quality metrics and control measurements to determine whether deliverables meet quality standards and whether quality processes are effective. Risk performance is assessed by reviewing the risk register to determine whether risk responses are being implemented, whether new risks are being identified, and whether overall risk exposure is increasing or decreasing. Resource performance examines whether resources are being utilized effectively and whether resource availability issues are affecting progress.
Performance reviews support several critical project management activities. They identify variances requiring corrective action by highlighting where performance deviates significantly from baselines. Reviews enable trend analysis by examining performance patterns over time to predict future performance.
Question 204:
Which agile ceremony focuses on continuous improvement of team processes and practices?
A) Sprint planning
B) Sprint review
C) Sprint retrospective
D) Daily standup
Correct Answer: C
Explanation:
The sprint retrospective is an agile ceremony held at the end of each sprint where the team reflects on their process, practices, tools, and interactions to identify specific improvements they can implement in the next sprint. This meeting embodies the agile principle of continuous improvement and team self-organization, enabling teams to incrementally refine their approach based on direct experience. Understanding sprint retrospectives is essential for project managers in agile environments because they represent the primary mechanism for process improvement and team development over time.
The sprint retrospective typically follows a structured format designed to create psychological safety and encourage honest reflection. A common approach examines what went well during the sprint that the team should continue doing, what did not go well that should be changed or stopped, and what the team should start doing that was not done during the sprint. The facilitator, often the scrum master, guides discussion to ensure all team members contribute their perspectives and that conversation remains constructive rather than becoming blame-focused. The emphasis is on team process, practices, and working environment rather than individual performance or project scope.
The retrospective serves multiple important purposes in agile team development and project execution. It provides a regular mechanism for process improvement, ensuring the team continuously evolves and adapts rather than repeating ineffective practices. The ceremony gives every team member a voice in how work is done, promoting engagement and ownership of the team’s approach. Retrospectives build team cohesion by creating shared understanding of challenges and collective commitment to improvements. They enable rapid learning with improvements implemented in the next sprint rather than waiting until project end when lessons cannot benefit current work.
Effective retrospectives require several conditions to be productive. Psychological safety must exist so team members feel comfortable sharing honest feedback without fear of negative consequences. All team members should actively participate rather than only vocal individuals dominating discussion. A skilled facilitator keeps the conversation productive and prevents defensive reactions.
Question 205:
What is the primary purpose of a project budget reserve in cost management?
A) To pay team salaries
B) To provide funds for identified risks and approved changes
C) To purchase equipment
D) To cover travel expenses
Correct Answer: B
Explanation:
Project budget reserves are funds set aside within the project budget to address uncertainties including identified risks, potential changes, and unforeseen circumstances that may arise during project execution. These reserves ensure that funds are available to respond to risks if they materialize or to implement approved changes without requiring additional budget approvals for every occurrence. Understanding budget reserves is important for project managers because they provide financial flexibility to manage uncertainty while maintaining overall budget control.
Project budgets typically include two types of reserves that serve different purposes and are managed differently. Contingency reserves are funds allocated for identified risks that have been analyzed and documented in the risk register. These reserves are calculated based on quantified risk exposure and stakeholder risk tolerance, often determined through risk analysis techniques such as expected monetary value calculation or Monte Carlo simulation. Contingency reserves are part of the project budget baseline and can be used by the project manager to respond to identified risks when they occur, within defined authority limits. For example, if a risk of vendor delay was identified and contingency was allocated for expedited shipping, the project manager can use those funds if the delay occurs.
Management reserves are funds set aside for unforeseen work that is within project scope but was not identified during planning. These reserves address unknown unknowns that could not have been anticipated or planned for. Management reserves are not included in the project budget baseline but are part of the total project budget. Unlike contingency reserves which the project manager can use within defined limits, management reserves require management approval before they can be accessed. This higher approval requirement reflects that management reserves address work that was not planned, requiring verification that it is truly within scope before funds are released.
Effective reserve management requires several practices to ensure reserves are used appropriately. Reserves should be calculated based on analysis rather than arbitrary percentages, with contingency amounts reflecting actual quantified risk exposure.
Question 206:
Which project management tool displays project activities as horizontal bars along a timeline?
A) Network diagram
B) Gantt chart
C) Pareto chart
D) Control chart
Correct Answer: B
Explanation:
A Gantt chart is a horizontal bar chart that displays project activities along a timeline, with each activity represented by a bar whose length indicates its duration and position shows its scheduled start and finish dates. This visual tool provides intuitive representation of the project schedule that is easily understood by team members and stakeholders without detailed project management knowledge. Understanding Gantt charts is essential for project managers because they are one of the most commonly used and universally recognized tools for communicating project schedules to diverse audiences.
The Gantt chart typically displays time periods such as days, weeks, or months on the horizontal axis and lists project activities or work packages on the vertical axis. Each activity is represented by a horizontal bar positioned along the timeline to show when the activity is scheduled to occur. The bar’s left edge indicates the planned start date, the bar’s right edge shows the planned finish date, and the bar length represents activity duration. Bars may be color-coded to indicate different types of activities, different project phases, or different responsible parties. Milestone events are often shown as diamond symbols or other markers at specific dates rather than as bars with duration.
Modern Gantt charts often include additional information beyond basic activity bars. Dependency relationships may be shown with arrows connecting related activities to indicate which activities must finish before others can start. Resource assignments can be displayed showing who is responsible for each activity. Progress indicators often show what percentage of each activity is complete, sometimes displayed as shading within the activity bar. The critical path may be highlighted in a distinctive color to show which activities directly affect project completion date. Today’s date may be marked with a vertical line enabling quick visual assessment of whether activities are ahead or behind schedule.
Gantt charts serve multiple purposes in project communication and management. They provide clear visual representation of the overall project timeline and duration that stakeholders can quickly understand. The charts show when specific activities will occur and how long they will take.
Question 207:
What is the primary purpose of a project organizational breakdown structure?
A) To decompose project work
B) To show which organizational units are responsible for work packages
C) To display the project schedule
D) To track project costs
Correct Answer: B
Explanation:
An organizational breakdown structure is a hierarchical representation of the project organization that shows which organizational units, departments, or teams are responsible for which portions of the project work. This structure maps the work breakdown structure to the organizational structure, creating clear assignment of work packages to responsible organizational entities. Understanding organizational breakdown structures is relevant for project managers because clear organizational responsibility supports accountability and effective coordination, particularly in large projects involving multiple departments or organizations.
The organizational breakdown structure typically mirrors the project’s organizational structure, starting with the highest level such as the project sponsor or steering committee at the top, then showing major organizational units or divisions at the second level, and continuing downward through departments, teams, or functional groups at lower levels. At the lowest level, the structure identifies specific organizational units responsible for individual work packages or groups of work packages from the work breakdown structure. This mapping creates explicit connection between project work and organizational responsibility.
The organizational breakdown structure serves multiple important purposes in project organization and management. It provides clarity about which organizational units are responsible for which portions of project work, preventing confusion about accountability. The structure supports resource planning by showing which organizational units need to provide resources for different work packages, enabling coordination with functional managers who control those resources. It facilitates communication by establishing clear organizational channels for coordinating work, resolving issues, and making decisions. The structure enables cost tracking by organizational unit, supporting analysis of which parts of the organization are consuming what portions of the project budget.
The organizational breakdown structure works in conjunction with the responsibility assignment matrix to create comprehensive accountability. While the organizational breakdown structure shows which organizational units are responsible for work packages, the responsibility assignment matrix drills down to show which specific individuals within those units have different types of responsibility for activities.
Question 208:
Which risk analysis tool plots risks on a grid based on probability and impact?
A) Decision tree
B) Probability and impact matrix
C) Tornado diagram
D) Influence diagram
Correct Answer: B
Explanation:
A probability and impact matrix is a tool used in qualitative risk analysis to prioritize risks by plotting them on a grid that displays their assessed probability of occurrence on one axis and their potential impact on project objectives on the other axis. This visual representation enables quick identification of which risks require the most management attention and response planning. Understanding the probability and impact matrix is essential for project managers because systematic risk prioritization ensures resources are focused on the most significant threats and opportunities rather than being diluted across all identified risks regardless of importance.
The probability and impact matrix uses a grid structure with probability levels displayed on one axis, typically categorized as very low, low, medium, high, and very high, or represented numerically such as 10 percent, 30 percent, 50 percent, 70 percent, and 90 percent. Impact levels are shown on the other axis using similar categorization to indicate the magnitude of effect on project objectives if the risk occurs. Each cell in the grid represents a specific combination of probability and impact and is assigned a priority rating, often indicated through color coding. Red zones represent high-priority risks requiring immediate attention and active response planning. Yellow zones indicate medium-priority risks that should be monitored and may require response plans. Green zones show low-priority risks that may be accepted with minimal active management.
The matrix serves multiple critical functions in project risk management. It provides visual representation that makes risk priorities immediately apparent to project managers and stakeholders without requiring detailed review of individual risk descriptions. The tool supports systematic risk prioritization by evaluating each risk against consistent criteria rather than relying on subjective impressions or political factors. The matrix facilitates risk communication by providing a common framework that all stakeholders understand, enabling discussions about risk to reference a shared visual representation.
The matrix enables consistent risk assessment across the project team by providing defined scales and categories that multiple assessors can apply.
Question 209:
What is the primary purpose of a project float calculation in schedule management?
A) To identify project costs
B) To determine how much activities can be delayed without affecting project completion
C) To assign resources to activities
D) To validate deliverables
Correct Answer: B
Explanation:
Float, also called slack, is a schedule management calculation that determines the amount of time an activity can be delayed from its early start date without delaying the project finish date or violating a schedule constraint. This calculation identifies scheduling flexibility and is fundamental to critical path analysis and schedule optimization. Understanding float is essential for project managers because it reveals which activities are critical to meeting the project deadline and which have flexibility that can be used for resource optimization or risk management.
Float calculations produce several types of measures that provide different insights into scheduling flexibility. Total float represents the amount of time an activity can be delayed without delaying the project completion date or violating a late finish constraint. Activities on the critical path have zero or negative float, meaning any delay directly impacts project completion. Activities with positive float have scheduling flexibility and are not on the critical path. Free float represents the amount of time an activity can be delayed without delaying the early start of any successor activity. This measure shows flexibility that does not affect other activities even if it does not extend to the project end date.
Float calculations enable several important project management capabilities. They identify the critical path by revealing which activities have zero float and therefore directly determine project duration. Understanding critical activities helps project managers focus attention and resources on work that cannot be delayed without project impact. Float reveals scheduling flexibility for non-critical activities, showing where delays can be accommodated or where activities can be rescheduled to resolve resource conflicts without affecting project completion. The calculations support resource optimization by showing which activities can be delayed to free up resources for critical work or to smooth resource utilization across time.
Float provides buffer against uncertainty by showing where schedule contingency exists naturally within the schedule logic. Activities with significant float can absorb delays from risk events without triggering project delays, while activities with zero float have no buffer.
Question 210:
Which project document records agreements reached and action items assigned during meetings?
A) Status report
B) Meeting minutes
C) Issue log
D) Decision log
Correct Answer: B
Explanation:
Meeting minutes are a project document that records what transpired during meetings including attendees, topics discussed, decisions made, action items assigned, and next steps. This official record ensures shared understanding of meeting outcomes and creates accountability for follow-up actions. Understanding meeting minutes is essential for project managers because systematic documentation supports coordination, prevents misunderstandings about agreements, and enables people who could not attend to stay informed about project developments.
Meeting minutes capture several categories of information that create comprehensive record of meeting proceedings. Basic meeting information includes the date, time, location, meeting type and purpose, and list of attendees present and absent. This context helps readers understand the meeting circumstances and who participated in discussions and decisions. The agenda items discussed are documented along with key points from each discussion, though minutes should summarize rather than transcribe every word spoken. The goal is capturing essential information and outcomes rather than creating verbose records of everything said.
Decisions made during the meeting are explicitly documented, including what was decided, who made or approved the decision, and any important context or conditions affecting the decision. This creates a definitive record that can be referenced if questions arise later about what was agreed. Action items represent critical content in meeting minutes, documenting specific tasks that must be completed after the meeting. For each action item, minutes should specify what action is required in clear, specific terms, who is responsible for completing the action, when the action is due, and any dependencies or prerequisites that must be satisfied before the action can be completed.
Issues or risks raised during the meeting are noted along with how they will be addressed, ensuring concerns are not lost or forgotten. Items requiring follow-up or future discussion are documented for inclusion in subsequent meeting agendas. Announcements or information shared during the meeting may be summarized for those who were absent.